Question: a ) Using the FCFS ( first come, first served ) decision rule for sequencing b ) Using the SPT ( shortest processing time )
a Using the FCFS first come, first served decision rule for sequencing b Using the SPT shortest processing time decision rule for sequencing
the jobs, the order is to resolve a tie, use the order in which the jobs
were received:
The average tardiness job lateness for the sequence developed using the SPT
rule days round your response to two decimal places
The average completion time for the sequence developed using the SPT rule
days round your response to two decimal places
The percentage utilization for the sequence developed using the SPT rule
enter your response as a percentage rounded to two decimal places c Using the EDD earliest due date decision rule for sequencing the jobs, the
order is to resolve a tie, use the order in which the jobs were received:
The average tardiness job lateness for the sequence developed using the
EDD rule days round your response to two decimal places
The average completion time for the sequence developed using the EDD rule :
days round your response to two decimal places
The percentage utilization for the sequence developed using the EDD rule
enter your response as a percentage rounded to two decimal places d Using the Critical Ratio CR scheduling rule for sequencing the jobs, the
order is:
The average tardiness job lateness for the sequence developed using the CR
rule days round your response to two decimal places
The average completion time for the sequence developed using the CR rule
days round your response to two decimal places
The percentage utilization for the sequence developed using the CR rule
enter your response as a percentage rounded to two decimal places
the jobs, the order is assume that jobs came in the order in which they are
listed in the table:
The average tardiness job lateness for the sequence developed using the
FCFS rule days round your response to two decimal places
The average completion time for the sequence developed using the FCFS
rule days round your response to two decimal places
The percentage utilization for the sequence developed using the FCFS rule
enter your response as a percentage rounded to two decimal places
b Using the SPT shortest processing time decision rule for sequencing
An Alabama lumberyard has four jobs on order, as shown in the following
table. Jobs are logged as they arrive. Today is day on the yard's
schedule. In what sequence would the jobs be ranked according to the
decision rules on the left:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock