Question: a ) Using the FCFS ( first come, first served ) decision rule for sequencing b ) Using the SPT ( shortest processing time )

a) Using the FCFS (first come, first served) decision rule for sequencing b) Using the SPT (shortest processing time) decision rule for sequencing
the jobs, the order is (to resolve a tie, use the order in which the jobs
were received):
The average tardiness (job lateness) for the sequence developed using the SPT
rule =, days (round your response to two decimal places).
The average completion time for the sequence developed using the SPT rule =
days (round your response to two decimal places).
The percentage utilization for the sequence developed using the SPT rule =
%(enter your response as a percentage rounded to two decimal places). c) Using the EDD (earliest due date) decision rule for sequencing the jobs, the
order is (to resolve a tie, use the order in which the jobs were received):
The average tardiness (job lateness) for the sequence developed using the
EDD rule = days (round your response to two decimal places).
The average completion time for the sequence developed using the EDD rule :
days (round your response to two decimal places).
The percentage utilization for the sequence developed using the EDD rule =
%(enter your response as a percentage rounded to two decimal places). d) Using the Critical Ratio (CR) scheduling rule for sequencing the jobs, the
order is:
The average tardiness (job lateness) for the sequence developed using the CR
rule =, days (round your response to two decimal places).
The average completion time for the sequence developed using the CR rule =
days (round your response to two decimal places).
The percentage utilization for the sequence developed using the CR rule =
%(enter your response as a percentage rounded to two decimal places).
the jobs, the order is (assume that jobs came in the order in which they are
listed in the table):
The average tardiness (job lateness) for the sequence developed using the
FCFS rule = days (round your response to two decimal places).
The average completion time for the sequence developed using the FCFS
rule =, days (round your response to two decimal places).
The percentage utilization for the sequence developed using the FCFS rule =
%(enter your response as a percentage rounded to two decimal places).
b) Using the SPT (shortest processing time) decision rule for sequencing
An Alabama lumberyard has four jobs on order, as shown in the following
table. Jobs are logged as they arrive. Today is day 1 on the yard's
schedule. In what sequence would the jobs be ranked according to the
decision rules on the left:
 a) Using the FCFS (first come, first served) decision rule for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!