Question: a) Using the FCFS (first come, first served ) decision rule for The following jobs are waiting to be processed at the same sequencing the

a) Using the FCFS (first come, first served ) decision rule for The following jobs are waiting to be processed at the same sequencing the jobs, the order is (assume that jobs came in the order machine center. Jobs are logged as they arrive: in which they are listed in the table): All dates are specified as manufacturing planning calendar days. Assume that all jobs arrive on day 275 . Assume each job starts at the beginning of the day and finishes at the end of the day (a job that begins on day 275 and takes 8 days will finish The average tardiness (job lateness) for the sequence developed on day 282 , and the next job begins in the morning of using the FCFS rule = days (round your response to two day 283). Compute all times based on initiating work on day decimal places). 275