Question: a. Using the spaces in the above chart, determine the earliest and latest starts and finishes for all activities. Determine the slack for all activities.

a. Using the spaces in the above chart, determine

a. Using the spaces in the above chart, determine the earliest and latest starts and finishes for all activities. Determine the slack for all activities. b. Which steps are on the Critical Path? c. What is the expected project completion time?

Assembling a guitar requires 5|activities. They are below: Activity Time Activity Predecessor (minutes) ES EF LS EF Slack --- 5 A B B --- 8 00 C A 3 D B 7 E C D 6