Question: A (Weighted) PERT Estimate: PERT: Program (or Project) Evaluation and Review Technique Mean = O+ 4ML + P 6 45 + 240 + 150 =

A (Weighted) PERT Estimate: PERT: Program (or Project) Evaluation and Review Technique Mean = O+ 4ML + P 6 45 + 240 + 150 = 72.5 Mins 6