Question: a) What is the bottleneck? b) Bottleneck time is ____ min/unit? c) What is the throughput time for the overall system? A production process at
a) What is the bottleneck?
b) Bottleneck time is ____ min/unit?
c) What is the throughput time for the overall system?
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 6 units/hr 7 units/hr Sawing Assembly 0.7 units/hr Sanding Welding 1.8 units/hr Assembly 0.7 units/hr Drilling 2.5 units/hr Assembly 0.7 units/hrStep by Step Solution