Question: a ) What is the current maximum output ( capacity ) of the process? [ Select ] [ 1 2 0 orders

a) What is the current maximum output ("capacity") of the process?
[ Select ]
["120 orders per day", "4 min per order", "240 orders per day", "160 orders per day"]
b) What is the total flow time?
[ Select ]
["10 min", "1 min", "4 min", "3 min"]
c) What is the total cycle time?
[ Select ]
["4min", "10 min", "2min", "3 min"]
d) Is there a benefit if we shift 1 min from grind beans to the order taking step? (e.g., make grinding beans take less time)
[ Select ]
["No", "Yes", "Not enough information"]
e) Is there any benefit if we shift 1 min from toppings to the add lid step? (e.g., make toppings take less time)
[ Select ]
["Yes","No", "Unable to answer with current information"]
f) Go back to the original problem. If we add another person, where would we add him/her?
[ Select ]
["Toppings", "Order", "Grind", "Lid"]
What would the benefit be?
[ Select ]
["Capacity increases by 40 orders/day","No change", "Capacity increases by 20 orders/day", "Capacity doubles"]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!