Question: A) What is the estimated mean time for project completion? B) What are the estimated slack times for activities A-H? C) What is the critical

A) What is the estimated mean time for project completion?
B) What are the estimated slack times for activities A-H?
C) What is the critical path for this project network?
D) What is the estimated standard deviation for the CRITICAL PATH completion time?
E) What is the probability that the critical path for this project will be completed within 75 days? 80 days? 85 days? 90 days?
F) Within what amount of time is there a 90% probability that the critical path for this project will be completed? 95%? 99%?
Events (nodes) Times Activity Start Finish Optimistic Most Likely Pessimistic A 1 2. 9 15 27 B 1 3 13 21 29 2 4. 6 9 12 2 5 23 35 35 E 3 5 19 26 51 F 4 6 23 29 35 G 5 6 14 20 20 H 6 7 2 5 8Step by Step Solution
There are 3 Steps involved in it