Question: Note the six distinct path times and variances for a project PERT chart (individual activity times not shown): Path # Expected completion time (days) Variance

Note the six distinct path times and variancesNote the six distinct path times and variancesNote the six distinct path times and variances

Note the six distinct path times and variances for a project PERT chart (individual activity times not shown): Path # Expected completion time (days) Variance (days) 1 20 3.5 2 18 2.8 3 25 3.4 4 12 2.2 5 17 3.1 6 10 1.9 What is the probability of completing the project within 30 days (TC)? Z=(TC - Tey/Project Std Deviation, where TC = client desired completion time: Te=expected project completion time, Project standard deviation Sq. root of the Project Variance (critical path variance) 0.6577 0.9838 0.9034 0.8752 Given the following activity network: A2 A1 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the latest completion time of A3? Every task has to be done in order to complete the project. (Hint: Remember LCtime is the latest time by which you will have to complete that task - even though you may sometimes have a choice of doing it earlier) 7 weeks 13 weeks 10 weeks 15 weeks Given the following activity network: A2 A1 A3 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the latest start time of A3? All activities must be done in order to complete the project. (Hint: find out the latest completion time for A3, consider how long it takes to do, and then compute it's latest start time) 5 weeks 11 weeks 13 weeks 7 weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!