Question: a. What is the minimum-cost schedule for this project? 14. You are the manager of a project to improve a billing process at your firm.

a. What is the minimum-cost schedule for thisa. What is the minimum-cost schedule for this

a. What is the minimum-cost schedule for this project?

14. You are the manager of a project to improve a billing process at your firm. Table 7.7 contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after week 12. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) 5,000 8,000 4,000 6,000 4,000 4,000 Crash Cost ($) 8,000 10,000 4,000 12,000 7,000 B,C 7,000