Question: a. What is the minimum-cost schedule for this project? The minimum-cost schedule is 13 weeks. ( Enter your response as an integer. ) b. What

a. What is the minimum-cost schedule for this project?
The minimum-cost schedule is 13 weeks. (Enter your response as an integer.)
b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in part (a)?
You are the manager of a project to improve a billing process at your firm. The table below contains the data you will need to conduct a cost analysis of the project. Indirect costs are $1,200 per week, and penalty costs are $1,400 per week after week 12. Activity Immediate Predecessor(s) Normal Time (weeks) A 4 B 5 C A 1 D B 6 E B, C 7 F D 7 Crash Time (weeks) 1 3 1 3 Normal Cost Crash Cost ($) ($) 4,500 8,000 7,500 10,000 4,500 4,500 6,000 12,500 3,500 7,000 4,500 7,500 6 6 a. What is the minimum-cost schedule for this project? The minimum-cost schedule is weeks. (Enter your response as an integer.)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts