Question: a. What is the project's duration if only normal times are used? b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration

a. What is the project's duration if only normal times are used? a. What is the project's duration if only normal

b. What is the minimum-cost schedule?

With the minimum-cost schedule, the project duration is ____day(s).?

The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $150 per day. The company will incur a $200 per day penalty for each day the project lasts beyond day 14. O Normal Time Crash Time Crash Cost Immediate Activity Normal Cost (S) (days) (days) ($) Predecessor(s) 4 900 3 1,000 B 6 1,000 3 2.200 500 3 1,000 . D 3 1.200 1,500 B E 4 1,500 1,500 CD F 2 1 1,400 E G 4 900 1 1,500 E H 5 300 2 600 G 4 2 4 1,300 a. What is the project's duration if only normal times are used? The project duration is day(s). (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!