Question: Information concerning a project is given in the table below. Indirect project costs amount to $250 per day. The company will incur a $100 per

Information concerning a project is given in the table below. Indirect project costs amount to $250 per day. The company will incur a $100 per day penalty for each day the project lasts beyond day 14. What is the project's duration if only normal times are used? What is the minimum-cost schedule? What is the critical path for the minimum-cost schedule