Question: A : What is the target completion week? B : How much would you save in total project costs with your schedule? You are the

A: What is the target completion week?
B: How much would you save in total project costs with your schedule?
You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25 . In addition, your project team determined that indirect project costs are $1,500 per week. a. What would be your target completion week? The target completion week is week . (Enter your response as an integer.)Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
