Question: A) Which activities form the critical path? B) What is the probability of completion of the project AFTER week 40 Activity Preceding A BA C

A) Which activities form the critical path?
B) What is the probability of completion of the project AFTER week 40
A) Which activities form the critical path? B)
Activity Preceding A BA C A D E F G H 1 J K LL 1 C B F D. E G H 1.J LL Optimistic Probable Pessimist Time Time Time 7 9 14 2 2 8 8 12 16 3 5 10 4 8 10 4 8 16 14 5 6 2 2 6 4 2 a 8 3 2 8 6 2