Question: a.) Which activity is NOT on the critical path if estimated project time is 40days? b) what is the Slack for value 1 activity if

a.) Which activity is NOT on the critical path if estimated project time is 40days?
b) what is the Slack for value 1 activity if estimated project time is 40 days?
c) what is the total project time?
Activity Duration Activity-6 6 Activity-1 1 Activity-7 7 2 Activity-2 Activity-3 Activity-8 8 3 Activity-9 9 Activity-4 4 Activity-10 10 Activity-5 5 Activity-11 11 5 6 9 1 2 8 11 4 10