Question: a.) Which activity is NOT on the critical path if estimated project time is 40days? b) what is the Slack for value 1 activity if

a.) Which activity is NOT on the critical path if

a.) Which activity is NOT on the critical path if estimated project time is 40days?

b) what is the Slack for value 1 activity if estimated project time is 40 days?

c) what is the total project time?

Activity Duration Activity-6 6 Activity-1 1 Activity-7 7 2 Activity-2 Activity-3 Activity-8 8 3 Activity-9 9 Activity-4 4 Activity-10 10 Activity-5 5 Activity-11 11 5 6 9 1 2 8 11 4 10