Question: a) which is the bottleneck? b) The bottleneck time is __________ minutes per unit (round your response to two decimal places). c) The throughput time
a) which is the bottleneck?
b) The bottleneck time is
__________ minutes per unit (round your response to two decimal places).
c) The throughput time of the overall system is
__________minutes (round your response to two decimal places).
d) If the firm operates 10 hours per day, 20 days per month, the monthly capacity of the manufacturing process is
___________units (enter your response as a whole number).
A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with, the sawing and sanding, which are independent sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel). 5 units/hr 5 units/hr Sawing Assembly 0.8 units/hr Sanding Welding 2.1 units/hr Assembly 0.8 units/hr Drilling 2.5 units/hr Assembly 0.8 units/hr a) is the bottleneckStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts