Question: a . With the aid of an example, explain the term project crashing with reference to critical path duration of a project. b . Avenal
a With the aid of an example, explain the term project crashing with reference to critical path duration of a project.
b Avenal Construction is awarded a contract to put a medium sized bridge across Save River by Chibi Turnoff, and the activities it has to undertake to completion are given with the respective activity precedence as shown in Table Q:
Table Q: Bridge Construction Activity Precedence
tableActivityActivity Description,Duration,tableImmediatePredecessorsClosing road,BTemporary fencing,ACExcavating,ADErection of scaffoldings,B and CELowering steel work,CFCasting of concrete works,CGRemoving steel works off the site,E and DHRemove temporary fence,BJReopening the road,E and FKClearing the site,H G and J
i Construct the network diagram for the above activities.
ii Schedule the earliest start and earliest finish, as well as latest start and latest finish for each activity.
iii What is the critical duration for this project?
iv If activity is extended to duration of days, what is the effect on the critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock