Question: A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task? Discrete work required to complete parts of a project Work
A Work Breakdown Structure (WBS) identifies deliverables, activities, and tasks. Which statement describes a task?
-
Discrete work required to complete parts of a project
-
Work performed to complete or manage the deliverables for a project
-
A list that identifies the logical way to progress through work
-
Tangible and measurable outcome expected from a project