Question: A work cell is required to make 80 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour

A work cell is required to make 80 computerized diagnostic assemblies (for installation into hybrid automobiles) each day. The cell currently works an eight hour shift, of which seven hours are available for productive work. These assemblies require five operations, with times of 1.0, 1.8, 2.4, 2.5, and 1.4 minutes each. (a) What is takt time for this cell? (b) How many workers will be needed?

Step by Step Solution

3.38 Rating (157 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To address the question well calculate the required values in two parts a Takt time and b Number of ... View full answer