Question: A work center assigns tasks to 8 work stations. The total of all the task times is 22.4. If the cycle time used is 2.9,

A work center assigns tasks to 8 work stations.

A work center assigns tasks to 8 work stations. The total of all the task times is 22.4. If the cycle time used is 2.9, what is the efficiency of this configuration? (Round your answer to 1 decimal places.)