Question: Help please! A work center assigns tasks to 4 work stations. The total of all the task times is 11.5. If the cycle time used

Help please! A work center assigns tasks to 4Help please!

A work center assigns tasks to 4 work stations. The total of all the task times is 11.5. If the cycle time used is 3.3, what is the efficiency of this configuration? (Round your answer to 1 decimal places.) Efficiency %