Question: A work center containing 9 machines with the same capacity operates 3 shifts per day 4 days a week (5 hours per shift). This is
A work center containing 9 machines with the same capacity operates 3 shifts per day 4 days a week (5 hours per shift). This is the effective capacity. If the work center has a system efficiency of 68%, what is the expected production in hours per week? Select one:
to. 6.12
b. 40.80
c. 367.20
d. 13.60
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts