Question: A work center containing 5 machines with the same capacity operates 3 shifts per day 7 days a week (5 hours per shift). This is
A work center containing 5 machines with the same capacity operates 3 shifts per day 7 days a week (5 hours per shift). This is the effective capacity. If the work center has a system efficiency of 89%, what is the expected production in hours per week? Select one:
to. 93.45
b. 31.15
c. 4.45
d. 467.25