Question: A work centre uses an average of 8 0 0 pieces of a part per eight hours of production. Each container holds 7 0 pieces

A work centre uses an average of 800 pieces of a part per eight hours of production. Each container holds 70 pieces and the average lead time for replenishment of one container is 120 minutes. The manager has assigned a safety factor of 0.40. How many kanbans are needed?
4
32
64
96
 A work centre uses an average of 800 pieces of a