Question: A work element in the project plan requires 2 0 0 hours of labor each by four technicians. The technicians are paid $ 4 0

A work element in the project plan requires 200 hours of labor each by four technicians. The technicians are paid $40 per hour and incur an overhead rate equal to 50 percent of their direct labor charges. Based on this data, what is the direct cost?
8,000
16,000
32,000
48,000
 A work element in the project plan requires 200 hours of