Question: A work operation consisting of three elements has been subjected to a stopwatch time study. The recorded observations are shown in below table. By standard,

A work operation consisting of three elements has been subjected to a stopwatch time study. The recorded observations are shown in below table. By standard, the work time allowance for the operation is personal time 5%, raw materials delay 5%, and fatigue 10%.

Which job element works the slowest than its expected time?

Which job element works the fastest than its expected time?

What is the normal time for Job Element A?

What is the normal time for Job Element B?

What is the normal time for Job Element C?

What is the normal time of the work operation?

What is the standard time of the work operation?

Hint: remove unusual time

Job Element

Observations (minutes)

Performance Rating

1

2

3

4

5

A

1

3

9

2

1

90%

B

8

6

8

3

7

110%

C

5

5

4

6

5

80%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!