Question: A work system has five serial stations that have process times of 6, 9, 4, 10, and 8. To complete processing, a unit needs to

A work system has five serial stations that have

A work system has five serial stations that have process times of 6, 9, 4, 10, and 8. To complete processing, a unit needs to go through all stations. What is the process cycle time of the system? a) 27 b) 4 O c) 37 d) 10