Question: Develop the AON diagram for the below project information. a) Complete the forward path. What is the Early Finish Time (EF) of Activity D? b)
Develop the AON diagram for the below project information.

a) Complete the forward path. What is the Early Finish Time (EF) of Activity D?
b) What is the Early Start Time (ES) of Activity H?
c) What is the duration of this project?
d) Complete the backward path. What is the Late Start Time of Activity I?
e) What is the Late Finish Time of Activity A?
f) What is the Total Float of Activity E?
g) What is the Total Float of Activity G?
h) What is the Free Float of Activity E?
i) What is the Free Float of Activity G?
j) What is the critical path?
Activity Predecessor Duration (weeks) 3 4 10 A,B 9 - 1 B 5 D 12 DE 7 C, F, G 9 C, G 5 J HT 8Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
