Question: A work system has five stations that have process times of 5 , 8 , 5 , 8 , and 1 5 . Find the

A work system has five stations that have process times of 5,8,5,8, and 15.
Find the bottleneck station. Add 2 machines to that station. What is the new bottleneck time?
Input should be an exact number (for example, 5 or 10).