Question: A . Your factory is working two 1 0 - hour shifts with one 3 0 minute lunch break and TwO 1 0 - minute
A Your factory is working two hour shifts with one minute lunch break and TwO minute additional breaks. Assume an efficiency of and a demand of units of Assembly A required per day. What is the TAKT?
B Using the BOM and the routings on the following pages, create and submit a ProductProcess matrix complete with the TOTAL NUMBER OF EACH MACHINES REQUIRED for our facility. Preferred format of this submission is Excel please submit the file so that I can review the calculations used in the cells CAUTION NOTE THE QUANTITIES OF EACH COMPONENT!
Place all components into a single table looking for a total number of machines for all camponents made.
Component Routings