Question: A(12) B (26) 2 E (18) C(10) D (10) 56 days > For the above network assume that the provided activity durations are for nearly


A(12) B (26) 2 E (18) C(10) D (10) 56 days > For the above network assume that the provided activity durations are for nearly 100% probability of completion. The figure is not to scale. The project buffer using Critical Chain Project Scheduling for this network is.... O 13 days O 14 days O 9 days O 26 days