Question: A3 A4 A6 A1 AZ A8 A2 AS Consider the AON graph of a project shown above. The activity times are 3, 5, 3, 7,

A3 A4 A6 A1 AZ A8 A2 AS Consider the AON graph of

A3 A4 A6 A1 AZ A8 A2 AS Consider the AON graph of a project shown above. The activity times are 3, 5, 3, 7, 7, 1, 3, 2 days for activities A1 through A8 respectively. What is the earliest completion time of the project? days