Question: ABC Builders have the below data about their project: BAC = $ 28,000 EV = $ 15,000 PV = $ 17,000 AC = $19,000 Calculate
ABC Builders have the below data about their project: BAC = $ 28,000 EV = $ 15,000 PV = $ 17,000 AC = $19,000 Calculate EAC if both SPI and CPI influence the project. Group of answer choices $37,840 $32,616 $41,915 -$41,915 -$34,820