Question: ABC Ltd. wants to develop aggregate production plan with chase strategy by changing workforce for a 4 month planning horizon. The demand and working days
ABC Ltd. wants to develop aggregate production plan with chase strategy by changing workforce for a 4 month planning horizon. The demand and working days are given below:
| Month | Demand | Days |
| January | 2200 | 22 |
| February | 1000 | 24 |
| March | 2100 | 25 |
| April | 1800 | 19 |
ABC is running 10 hours a day. Production of one unit require 2 hours.
Write down the number of workers required for January in the aggregate production plan.