Question: ABC Ltd. wants to develop aggregate production plan with constant workforce (no overtime or subcontract) for a 4 month planning horizon. The demand and working
ABC Ltd. wants to develop aggregate production plan with constant workforce (no overtime or subcontract) for a 4 month planning horizon. The demand and working days are given below:
| Month | Demand | Days |
| January | 900 | 21 |
| February | 1200 | 23 |
| March | 1000 | 24 |
| April | 1400 | 22 |
ABC is running 10 hours a day. Production of one unit require 2 hours.
Write down the production units in January in the aggregate production plan.