Question: ABC Technology Development Company has signed a contract for development and delivery of a software package to increase the productivity of a client company. The

ABC Technology Development Company has signed a contract for development and delivery of a software package to increase the productivity of a client company. The agile project team, during the planning cycle has come with the following data/information: Estimated total story points: 2000 points EPIC 1: 1200 story points EPIC 2: 800 story points Average story points to be delivered per sprint: 200 Scrum team size: 4 Planned sprint duration 4 weeks If the epics could be run in parallel or concurrently, what is the estimated project duration