Question: QUESTION 11 ABC Technology Development Company has signed a contract for development and delivery of a software package to increase the productivity of a client

QUESTION 11

  1. ABC Technology Development Company has signed a contract for development and delivery of a software package to increase the productivity of a client company. The agile project team, during the planning cycle has come with the following data/information:

    Estimated total story points: 2000 points

    EPIC 1: 1200 story points

    EPIC 2: 800 story points

    Average story points to be delivered per sprint: 200

    Scrum team size: 4

    Planned sprint duration 4 weeks

    If the epics could be run in parallel or concurrently, what is the estimated project duration.

    24 Weeks

    40 Weeks

    32 Weeks

    16 Weeks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!