Question: QUESTION 11 ABC Technology Development Company has signed a contract for development and delivery of a software package to increase the productivity of a client
QUESTION 11
-
ABC Technology Development Company has signed a contract for development and delivery of a software package to increase the productivity of a client company. The agile project team, during the planning cycle has come with the following data/information:
Estimated total story points: 2000 points
EPIC 1: 1200 story points
EPIC 2: 800 story points
Average story points to be delivered per sprint: 200
Scrum team size: 4
Planned sprint duration 4 weeks
If the epics could be run in parallel or concurrently, what is the estimated project duration.
24 Weeks
40 Weeks
32 Weeks
16 Weeks
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
