Question: About project schedules, which one is true: events represent a moment in time, such as the start or finish of something activities or tasks represent

About project schedules, which one is true:
"events" represent a moment in time, such as the start or finish of something
"activities" or "tasks" represent the actual doing of work and the passage of time
both (a) and (b)
neither (a) nor (b)
 About project schedules, which one is true: "events" represent a moment