Question: accepted in doc or pdf format only. Total marks 20 Q1. How many milestones are there in the project. Name them. Marks 4 Ans 1.

accepted in doc or pdf format only. Total marks 20 Q1. How many milestones are there in the project. Name them. Marks 4 Ans 1. Q2. What is the duration provided for Impementation of the Software. Marks 2 Ans 2. Q3. What is the total duration of the project from Analysis to Completion. Marks 2 Ans 3. Q4. Identify the Level 1 WBS and name them Marks 5 Ans 4. Q5. How many activities are 100% complete Marks 2 Ans 5. Q6. How many priroties has the cheudkler assigned in this project? Marks 2 Ans 6. Q7. How many members are there in the team, identify them and indicate how many activities has been assigned to each of them