Question: accepted in doc or pdf format only. Total marks 20 Q1. How many milestones are there in the project. Name them. Marks 4 Ans 1.

 accepted in doc or pdf format only. Total marks 20 Q1.

accepted in doc or pdf format only. Total marks 20 Q1. How many milestones are there in the project. Name them. Marks 4 Ans 1. Q2. What is the duration provided for Impementation of the Software. Marks 2 Ans 2. Q3. What is the total duration of the project from Analysis to Completion. Marks 2 Ans 3. Q4. Identify the Level 1 WBS and name them Marks 5 Ans 4. Q5. How many activities are 100% complete Marks 2 Ans 5. Q6. How many priroties has the cheudkler assigned in this project? Marks 2 Ans 6. Q7. How many members are there in the team, identify them and indicate how many activities has been assigned to each of them

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!