Question: According to attached work breakdown structure ( WBS ) and resource sheet related with the PV Solar Plant Project : 1 . Schedule the activities

According to attached work breakdown structure (WBS) and resource sheet related with the PV Solar Plant Project :
1. Schedule the activities
2. Assign resources to activities and schedule resources
by using MS Project Professional.
Homework will be submitted in .mpp format.
WBS-PV Solar Energy
# Task Name Duration (dys) Predecessors Note
1 PV Solar Plant Installation and Commissioning Project name
2 Feasibility and Before Installation Summary task
3 Starting the project 0-|5 days calendar
4 Establishment of the project management office 53|5 days calendar
5 Feasibility analysis 154SS+2 days |6 days calendar
6 Call letter application to the relevant distribution company 205|5 days calendar
7 Getting project approval from TEDA306|5 days calendar
8 Signing a connection agreement with the distribution company 107FF+5days |5 days calendar
9 Assembly and commissioning of the plant Summary task
10 Installation of the plant 128|6 days calendar
11 Acceptance of the facility by TEDA1510|5 days calendar
12 Signing a system usage agreement with the distribution company 811|5 days calendar
13 Commissioning of the production facility 1012|5 days calendar
14 Completion of the project 013|5 days calendar
# Task Name Resource Initials Resource Amounts
1 PV Solar Plant Installation and Commissioning
2 Feasibility and Before Installation
3 Starting the project
4 Establishment of the project management office PY (1 Unit)
5 Feasibility analysis PY, EM, IM (1,1,1 Unit)
6 Call letter application to the relevant distribution company GH 20000 TL
7 Getting project approval from TEDA GH 30000 TL
8 Signing a connection agreement with the distribution company PY, GH (1 Unit, 10000 TL)
9 Assembly and commissioning of the plant
10 Installation of the plant EM, IM, GH, PP, INV (1,1 Unit; 40000 TL; 40,2 Unit)
11 Acceptance of the facility by TEDA PY, GH (1 Unit, 10000 TL)
12 Signing a system usage agreement with the distribution company PY, GH (1 Unit, 10000 TL)
13 Commissioning of the production facility PY, GH (1 Unit, 10000 TL)
14 Completion of the project
Resource Name Type Material Label Initial Max St. Rate (TL/h) Ovt. Rate (TL/h)
Project Manager Work PY 1120150
Electrical Electronics Engineer Work EM 180100
Civil Engineer Work IM 180100
PV Solar Plant Installation Service Procurement Cost GH
PV Panel (250W) Material PP 5000
Inverter Material INV 14000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!