Question: According to Critical Chain Project Management principles, project buffer protects ____ The critical chain activities from the effects of student syndrome by adding more slack
According to Critical Chain Project Management principles, project buffer protects ____
The critical chain activities from the effects of student syndrome by adding more slack to their durations
The project completion date against variation in the critical chain activities
The critical chain from variations in a non-critical project path
The project completion date against the negative effects of project multitasking
None of the above
The critical chain is identical to the critical path in a project where
Group of answer choices
There are no resource constraints
Activity durations are uncertain
A single time estimate for activity durations is used
A large number of employees is involved
There exists a large number of parallel paths through the project
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts