Question: According to following data, design a control chart and determine process is in or out-of-control. Time 1 2 3 4 5 6 7 Average of
According to following data, design a control chart and determine process is in or out-of-control.
| Time | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Average of length (cm) | 10.5 | 21.34 | 16.09 | 20.13 | 25.89 | 11.35 | 14.23 |
Note that, the UCL and LCL of the control chart are 25.44 and 11.17, respectively. In addition, the curtained customer target is also considered as 18.33.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts