Question: According to the following earned value analysis graph, the project at time period 2 is: Ahead of schedule and under budget. Behind schedule and under
According to the following earned value analysis graph, the project at time period 2 is:
| Ahead of schedule and under budget. | |
| Behind schedule and under budget. | |
| Ahead of schedule and over budget. | |
| Behind schedule and over budget. |