Question: You found the following earned value analysis information for a project that was recently closed - out: SPI = 0 . 7 , CPI =

You found the following earned value analysis information for a project that was recently closed-out: SPI =0.7, CPI =1.0
The project's deliverables have all been finished. The project came in on schedule but over budget.
The project has been canceled while it was executed. At that time the project was behind schedule and on budget.
The project's deliverables are not all finished. The project came in behind schedule (after due date) but on budget.
The project's deliverables have all been finished. The project came in ahead of schedule (before due date) but on budge