Question: According to the principles established in the Ron Engineering case, when does contract A come into existence? Question 11 options: When the owner invites a
According to the principles established in the Ron Engineering case, when does contract "A" come into existence?
Question 11 options:
|
| When the owner invites a contractor to bid on the work. |
|
| When the contractor submits a bid. |
|
| When the owner opens the bid. |
|
| When the owner sends a letter of intent to the contract. |
|
| When the owner awards the contract for work to the contractor. |
Question 12 (1 point)
Following the Ron Engineering case and subsequent cases, what are the established rules regarding subcontractor bids?
Question 12 options:
|
| A sub trade cannot withdraw its bid when the contractor has used the price in its bid to the owner. |
|
| A contractor has to award a contract to the sub trade whose price is used in the contractor's bid to the owner. |
|
| A contractor has to award a contract to the sub trade who is named in the contractor's bid to the owner. |
|
| A subcontractor can withdraw its bid with 30 days notice. |
Question 13 (1 point)
If there is a discrepancy between the words and the numbers used to state the contract price on the contract documents, the numbers written in words take precedence.
Question 13 options:
| True | |
| False |
Question 14 (1 point)
What are supplementary conditions in accordance with the CCDC-2 form of the contract?
Question 14 options:
|
| Supplementary conditions are clauses added to the specifications. |
|
| Supplementary conditions modify or replace the general conditions of the contract. |
|
| Supplementary conditions are causes the contractor adds to the owner's form of the contract. |
|
| Supplementary conditions are clauses added to the standard form of the contract after negotiations. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
