Question: According to the punctuated - equilibrium model, when does marked acceleration of activity occur? The time immediately hefore the official deadline Once trust has been

According to the punctuated-equilibrium model, when does marked acceleration of activity occur?
The time immediately hefore the official deadline
Once trust has been established between group members
During the group's first meeting
Halfway between the first meeting and the official deadline
At the end of Phase 1
 According to the punctuated-equilibrium model, when does marked acceleration of activity