Question: According to the table below Activity Predecessor/Relationship Duration Execution Month A - 3 1 B A (FS+5) 2 2 C A (SS+2) 1 2 D
According to the table below
| Activity | Predecessor/Relationship | Duration | Execution Month |
| A | - | 3 | 1 |
| B | A (FS+5) | 2 | 2 |
| C | A (SS+2) | 1 | 2 |
| D | C (FF) | 2 | 3 |
| D | B (SS+3) | 5 | 4 |
| F | E (FS), D (FS) | 2 | 5 |
Calculate:
1. Drawing the network diagram
2. Draw the Gantt Chart (you can see how to do it in the exercise
videos in week 7).
3. ES, EF, LS, LF, and the SL.
4. The critical path in two ways, looking for the
paths and the other traditional way.
5. Calculate clearances / Free slack