Question: According to the table below, which project is the most favorable when we use the weighted scoring model? Criteria / Projects Weight Project A Project

According to the table below, which project is the most favorable when we use the weighted scoring model? Criteria / Projects Weight Project A Project B Project C Project D Criterion 1 0.3 3 1 2 3 Criterion 2 0.4 2 3 2 3 Criterion 3 0.2 3 2 1 1 Criterion 4 0.1 1 1 3 3 Criteria / ProjectsWeightProject AProject BProject CProject D Criterion 10.33123 Criterion 20.42323 Criterion 30.23211 Criterion 40.11133 D A B C