Question: 1. What is the throughput time of the process? 2. What is the process capacity? 3. Would adding another unit of Screwup help increase the


1. What is the throughput time of the process?
2. What is the process capacity?
3. Would adding another unit of Screwup help increase the process capacity?
A Note: Numbers within parenthesis represent the average activity time in minutes. Any rework occurs only once. D (23) yoon 0X600] E (25) (26) (23) 0.7 0.3 B 0.15 (12) F (10) G (31) H (30) I (21) J (25) K (13) 0.05 L (10) M (15) N (18)
Step by Step Solution
3.48 Rating (161 Votes )
There are 3 Steps involved in it
1 ANS WER The average throughput time for the process is 21 minutes WORK ING 1 1 ... View full answer