Question: Ackerman's garage uses standards to plan and control labor time and expenses. The standard time for an engine tune-up is 3.5 hours, and the standard

Ackerman's garage uses standards to plan and control labor time and expenses. The standard time for an engine tune-up is 3.5 hours, and the standard labor rate is $19 per hour. last week, 24 tune-ups were completed. The laborefficiencyvariance was 13 hours unfavorable, and the labor rate variance totaled $85 favorable.

a- Calculate the actual direct labor hourly rate paid for tune-up work last week.

b- Calculate the dollar amount of the labor efficiency variance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock